Dept. of Trans. PROGRESS Serial No. Contract No. 23-167-21-57 11-2N1434 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 85% Location: Federal Project: 11-SD-78-12.8/R22.1 NONE Progress payment No. 010 Payment period ending: 06-20-23 HAZARD CONSTRUCTION ENGR LLC 10529 VINE ST LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,882,167.36 47,022.55 2. a. Extra Work 256,657.55 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,138,824.91 47,022.55 5. Mobilization 320,000.00 0.00 6. Total Work Completed 3,458,824.91 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,458,824.91 47,022.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 47,022.55