Dept. of Trans. PROGRESS Serial No. Contract No. 24-052-12-05 11-2N1654 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 100% Location: Federal Project: 11-SD-8-R61.0/R68.0 NONE Progress payment No. 006 Payment period ending: 02-20-24 ATP GENERAL ENGINEERING CONTRACTORS LLC 4211 PONDEROSA AVE #C SAN DIEGO CA 92123 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,835,485.96 127,293.54 2. a. Extra Work 53,094.44 46,836.82 b. Adustment Comp. -86,210.12 -86,210.12 3. Materials on Hand 4. Earned Subject to Retention 6,802,370.28 87,920.24 5. Mobilization 345,000.00 0.00 6. Total Work Completed 7,147,370.28 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,147,370.28 97,920.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 97,920.24