Dept. of Trans. PROGRESS Serial No. Contract No. 25-234-09-44 11-2N1784 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 42% Location: Federal Project: 11-IMP-8-R0.0/R10.3 NONE Progress payment No. 002 Payment period ending: 08-20-25 INTERMOUNTAIN SLURRY SEAL INC PO BOX 742298 LOS ANGELES CA 90074 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,800,335.37 1,786,235.37 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,800,335.37 1,786,235.37 5. Mobilization 470,250.00 470,250.00 6. Total Work Completed 2,270,585.37 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,270,585.37 2,256,485.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,256,485.37