Dept. of Trans. PROGRESS Serial No. Contract No. 24-257-12-20 11-2N2034 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 60% Location: Federal Project: 11-VAR NONE Progress payment No. 002 Payment period ending: 09-20-24 MONTANO PIPELINE INC 231 FOURTH AVE CHULA VISTA CA 91910 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 429,309.40 317,509.70 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 429,309.40 317,509.70 5. Mobilization 118,750.00 56,250.00 6. Total Work Completed 548,059.40 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 548,059.40 373,759.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 373,759.70