Dept. of Trans. PROGRESS Serial No. Contract No. 25-017-12-57 11-2N2054 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 36% Location: Federal Project: 11-VAR NONE Progress payment No. 002 Payment period ending: 01-20-25 HMS CONSTRUCTION INC 2885 SCOTT ST VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 152,216.10 94,308.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 152,216.10 94,308.60 5. Mobilization 32,782.50 10,927.50 6. Total Work Completed 184,998.60 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 184,998.60 105,236.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 105,236.10