Dept. of Trans. PROGRESS Serial No. Contract No. 26-084-11-30 11-2N2244 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 88% Location: Federal Project: 11-SD-79-L0.6/52.9 NONE Progress payment No. 006 Payment period ending: 03-20-26 GBA ENGINEERING INC 18543 YORBA LINDA BLVD 394 YORBA LINDA CA 92886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 517,670.00 32,220.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 517,670.00 32,220.00 5. Mobilization 38,000.00 0.00 6. Total Work Completed 555,670.00 7. Deductions -3,000.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 552,670.00 33,220.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,220.00