Dept. of Trans. PROGRESS Serial No. Contract No. 09-295-13-54 11-2T0004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 54% 11-SD-52-17.0/17.7 Federal Project: HPLU-6211(75) HPLU-6211(76) Progress payment No. 19 Payment period ending: 10-20-09 SKANSKA USA CIVIL WEST CALIFORNIA DISTRICT INC 1995 AGUA MANSA ROAD RIVERSIDE CA 925092405 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 35,203,315.04 2,770,512.56 2.a. Extra Work 216,867.14 30,922.82 b. Adjustment Comp. 167,316.68 1,031.94 3. Materials on Hand 1,070,125.39 -330,767.05 4. Earned Subject to Retention 36,657,624.25 2,471,700.27 5. Mobilization 6,600,000.00 0.00 6. Total Work Completed 42,187,498.86 7. Deductions -8,207.50 53,352.50 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 43,249,416.75 2,525,052.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,525,052.77