Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 11-213-11-31 11-2T0004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-52-17.0/17.7 Federal Project: HPLU-6211(75) HPLU-6211(76) Progress payment No. 37 Payment period ending: 06-27-11 SKANSKA USA CIVIL WEST CALIFORNIA DISTRICT INC 1995 AGUA MANSA ROAD RIVERSIDE CA 925092405 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 60,109,841.40 -1,390,577.34 2.a. Extra Work 2,812,692.85 832,903.03 b. Adjustment Comp. 2,781,675.47 397,196.44 3. Materials on Hand 4. Earned Subject to Retention 65,704,209.72 -160,477.87 5. Mobilization 6,600,000.00 0.00 6. Total Work Completed 72,304,209.72 7. Deductions -23,780.25 -13,572.75 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 72,280,429.47 -174,050.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -174,050.62