Dept. of Trans. PROGRESS Serial No. Contract No. 13-168-16-25 11-2T0014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-52-17.3/17.5 Federal Project: STPL-6211(103) N-6211(103) Progress payment No. 21 Payment period ending: 06-20-13 MIDORI LANDSCAPE INC 3231 S MAIN STREET SANTA ANA CA 92707 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 916,682.89 1,522.30 2.a. Extra Work 23,584.85 0.00 b. Adjustment Comp. 200.39 0.00 3. Materials on Hand 4. Earned Subject to Retention 940,468.13 1,522.30 5. Mobilization 49,060.00 0.00 6. Total Work Completed 989,528.13 7. Deductions -2,000.00 1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 987,528.13 2,522.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,522.30