Dept. of Trans. PROGRESS Serial No. Contract No. 12-052-11-40 11-2T0114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 59% 11-SD-52-15.5/17.3 Federal Project: STPL-6211(101) N-6211(101) Progress payment No. 06 Payment period ending: 02-20-12 GRIFFITH COMPANY 12200 BLOOMFIELD AVENUE SANTA FE SPRINGS CA 90670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 371,635.56 140,976.75 2.a. Extra Work 386.11 386.11 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 372,021.67 141,362.86 5. Mobilization 43,225.00 9,100.00 6. Total Work Completed 415,246.67 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 415,246.67 150,462.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 150,462.86