Dept. of Trans. PROGRESS Serial No. Contract No. 07-114-07-36 11-2T0204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-52-8.6/10.2 Federal Project: NONE Progress payment No. 07 Payment period ending: 04-20-07 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,563,231.18 1,363,653.43 2.a. Extra Work 43,157.94 9,748.28 b. Adjustment Comp. -39,000.00 -39,000.00 3. Materials on Hand 4. Earned Subject to Retention 2,567,389.12 1,334,401.71 5. Mobilization 300,000.00 15,000.00 6. Total Work Completed 2,867,389.12 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions -128,369.46 -66,720.09 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,719,019.66 1,272,681.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,272,681.62