Dept. of Trans. PROGRESS Serial No. Contract No. 07-204-14-04 11-2T0204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-52-8.6/10.2 Federal Project: NONE Progress payment No. 10 Payment period ending: 07-20-07 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,850,143.89 122,418.00 2.a. Extra Work 58,214.26 4,158.91 b. Adjustment Comp. -39,682.03 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,868,676.12 126,576.91 5. Mobilization 300,000.00 0.00 6. Total Work Completed 3,168,676.12 7. Deductions 0.00 6,191.22 8. a.Contract Retentions -143,433.81 -6,328.85 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,025,242.31 126,439.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 126,439.28