Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 07-211-09-39 11-2T0204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-52-8.6/10.2 Federal Project: NONE Progress payment No. 11 Payment period ending: 07-20-07 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,850,143.89 0.00 2.a. Extra Work 670,988.76 612,774.50 b. Adjustment Comp. -39,682.03 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,481,450.62 612,774.50 5. Mobilization 300,000.00 0.00 6. Total Work Completed 3,781,450.62 7. Deductions 8. a.Contract Retentions -174,072.53 -30,638.72 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,607,378.09 582,135.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 582,135.78