Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-234-14-29 11-2T0204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-52-8.6/10.2 Federal Project: NONE Progress payment No. 12 Payment period ending: 08-07-07 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,856,005.64 5,861.75 2.a. Extra Work 678,693.18 7,704.42 b. Adjustment Comp. -39,682.03 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,495,016.79 13,566.17 5. Mobilization 300,000.00 0.00 6. Total Work Completed 3,795,016.79 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -174,072.53 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 174,072.53 174,072.53 9. Total pay to Contractor 3,785,016.79 177,638.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 177,638.70