Dept. of Trans. PROGRESS Serial No. Contract No. 12-235-15-11 11-2T0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 47% 11-SD-805-26.5/28.9 Federal Project: ARRA-805(610) L-805(610) Progress payment No. 19 Payment period ending: 08-20-12 DIABLO CONTRACTORS INC 7 CROW CANYON COURT SUITE 100 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,648,980.72 967,593.15 2.a. Extra Work 748,622.01 79,310.95 b. Adjustment Comp. 394,553.61 0.00 3. Materials on Hand 843,920.34 -41,316.27 4. Earned Subject to Retention 28,636,076.68 1,005,587.83 5. Mobilization 4,000,000.00 0.00 6. Total Work Completed 31,792,156.34 7. Deductions -25,635.60 1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,610,441.08 1,006,587.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,006,587.83