Dept. of Trans. PROGRESS Serial No. Contract No. 16-021-16-01 11-2T0414 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 10% Location: Federal Project: 11-SD-805-26.8/27.3 NONE Progress payment No. 003 Payment period ending: 01-20-16 CLEAN CUT LANDSCAPE 8406 N. ARMSTRONG AVE. CLOVIS CA 93619 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 90,735.99 44,807.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 90,735.99 44,807.40 5. Mobilization 52,066.00 52,066.00 6. Total Work Completed 142,801.99 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 142,801.99 96,873.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 96,873.40