Dept. of Trans. PROGRESS Serial No. Contract No. 17-205-13-51 11-2T0414 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 53% Location: Federal Project: 11-SD-805-26.8/27.3 NONE Progress payment No. 021 Payment period ending: 07-20-17 CLEAN CUT LANDSCAPE INCORPORATED 7726 N FIRST ST UNIT 137 FRESNO CA 93720 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 630,679.35 4,641.78 2. a. Extra Work 165,634.47 2,424.16 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 796,313.82 7,065.94 5. Mobilization 104,132.00 0.00 6. Total Work Completed 900,445.82 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 900,445.82 7,065.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,065.94