Dept. of Trans. PROGRESS Serial No. Contract No. 25-108-12-13 11-2T0444 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 14% Location: Federal Project: 11-SD-5-R4.4/R4.5 NONE Progress payment No. 008 Payment period ending: 04-12-25 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,794,554.68 2,869,375.49 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 20,794,554.68 2,869,375.49 5. Mobilization 9,576,000.00 2,016,000.00 6. Total Work Completed 30,370,554.68 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,350,554.68 4,885,375.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,885,375.49