Dept. of Trans. PROGRESS Serial No. Contract No. 25-262-11-03 11-2T0444 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 23% Location: Federal Project: 11-SD-5-R4.4/R4.5 NONE Progress payment No. 013 Payment period ending: 09-20-25 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,692,518.92 3,989,621.94 2. a. Extra Work 9,909.92 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 28,702,428.84 3,989,621.94 5. Mobilization 9,576,000.00 0.00 6. Total Work Completed 38,278,428.84 7. Deductions -15,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 38,263,428.84 3,984,621.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,984,621.94