Dept. of Trans. PROGRESS Serial No. Contract No. 26-050-12-10 11-2T0444 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 31% Location: Federal Project: 11-SD-5-R4.4/R4.5 NONE Progress payment No. 018 Payment period ending: 02-20-26 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 44,965,486.36 5,125,020.61 2. a. Extra Work 20,363.98 0.00 b. Adustment Comp. -16,000.00 -16,000.00 3. Materials on Hand 4. Earned Subject to Retention 44,969,850.34 5,109,020.61 5. Mobilization 9,576,000.00 0.00 6. Total Work Completed 54,545,850.34 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 54,525,850.34 5,109,020.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,109,020.61