Dept. of Trans. FINAL Serial No. Contract No. 15-287-15-31 11-2T0704 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 11-SD-52-14.5/15.5 STPL-N621(110) Progress payment No. 040 Payment period ending: 01-15-15 MIDORI LANDSCAPE INC 3231 S MAIN STREET SANTA ANA CA 92707 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,791,395.35 0.00 2. a. Extra Work 38,157.51 2,197.83 b. Adustment Comp. -21,080.40 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,808,472.46 2,197.83 5. Mobilization 87,686.00 0.00 6. Total Work Completed 1,896,158.46 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,896,158.46 12,197.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,197.83