Dept. of Trans. PROGRESS Serial No. Contract No. 10-236-10-28 11-2T0824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 59% 11-SD-15-R30.0/R31.5 Federal Project: CIM-015-4(202) CMLN-6211(53) Progress payment No. 23 Payment period ending: 08-20-10 ATKINSON CONTRACTORS L P 27422 PORTOLA PARKWAY STE 250 FOOTHILL RANCH CA 92610 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,983,520.27 891,645.59 2.a. Extra Work 324,263.77 28,320.85 b. Adjustment Comp. 160,040.42 7,762.50 3. Materials on Hand 605,382.42 -117,196.34 4. Earned Subject to Retention 31,073,206.88 810,532.60 5. Mobilization 4,600,000.00 0.00 6. Total Work Completed 35,067,824.46 7. Deductions -23,147.00 -2,725.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 35,650,059.88 807,807.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 807,807.60