Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 12-212-14-11 11-2T0824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-15-R30.0/R31.5 Federal Project: CIM-015-4(202) CMLN-6211(53) Progress payment No. 44 Payment period ending: 06-27-12 ATKINSON CONTRACTORS L P 27422 PORTOLA PARKWAY STE 250 FOOTHILL RANCH CA 92610 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,316,188.55 4,640.00 2.a. Extra Work 2,670,515.89 3,352.07 b. Adjustment Comp. -328,132.46 -28,860.38 3. Materials on Hand 4. Earned Subject to Retention 45,658,571.98 -20,868.31 5. Mobilization 4,600,000.00 0.00 6. Total Work Completed 50,258,571.98 7. Deductions -92,308.23 -20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 50,166,263.75 -40,868.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -40,868.31