Dept. of Trans. PROGRESS Serial No. Contract No. 12-116-11-19 11-2T0864 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 7% 36% 11-SD-15-M26.2/M27.8 Federal Project: NONE Progress payment No. 01 Payment period ending: 04-20-12 PACIFIC RESTORATION GROUP INC P O BOX 429 PERRIS CA 92572 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 54,582.00 54,582.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 54,582.00 54,582.00 5. Mobilization 18,500.00 18,500.00 6. Total Work Completed 73,082.00 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 72,082.00 72,082.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 72,082.00