Dept. of Trans. PROGRESS Serial No. Contract No. 09-055-14-17 11-2T0914 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 24% 11-SD-15-R10.5/M15.0 Federal Project: NONE Progress payment No. 08 Payment period ending: 02-20-09 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 02382 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,196,892.05 947,045.22 2.a. Extra Work 1,074,831.79 20,533.73 b. Adjustment Comp. -66,311.13 0.00 3. Materials on Hand 1,825,392.64 234,407.89 4. Earned Subject to Retention 12,030,805.35 1,201,986.84 5. Mobilization 3,733,500.00 0.00 6. Total Work Completed 13,938,912.71 7. Deductions -31,020.00 0.00 8. a.Contract Retentions -926,609.55 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,806,675.80 1,201,986.84 10. Reduction Amt to Escrow 11. Payment to Escrow 926,600.00 12. Net Pymt. this Estimate 1,201,986.84