Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-319-09-33 11-2T0914 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-15-R10.5/M15.0 Federal Project: NONE Progress payment No. 41 Payment period ending: 05-31-11 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 02382 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,194,273.00 66,745.20 2.a. Extra Work 5,964,988.69 58,205.69 b. Adjustment Comp. 79,285.06 500.00 3. Materials on Hand 4. Earned Subject to Retention 52,238,546.75 125,450.89 5. Mobilization 3,930,000.00 0.00 6. Total Work Completed 56,168,546.75 7. Deductions -260,163.58 0.00 8. a.Contract Retentions -2,571,044.57 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,571,044.57 0.00 9. Total pay to Contractor 55,908,383.17 125,450.89 10. Reduction Amt to Escrow -2,571,040.00 0.00 11. Payment to Escrow 2,571,040.00 12. Net Pymt. this Estimate 125,450.89