Dept. of Trans. PROGRESS Serial No. Contract No. 09-055-14-17 11-2T0924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 9% 11-SD-15-M10.4/R21.2 Federal Project: NONE Progress payment No. 06 Payment period ending: 02-20-09 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA, STE 200 SAN DIEGO CA 92126 Escrow No. 02397 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,780,370.67 1,681,221.08 2.a. Extra Work 92,744.90 27,926.08 b. Adjustment Comp. 3. Materials on Hand 518,484.39 -214,602.47 4. Earned Subject to Retention 8,391,599.96 1,494,544.69 5. Mobilization 4,506,006.23 0.00 6. Total Work Completed 12,379,121.80 7. Deductions -20,000.00 10,000.00 8. a.Contract Retentions -839,160.00 -149,454.47 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,038,446.19 1,355,090.22 10. Reduction Amt to Escrow 11. Payment to Escrow 839,160.00 12. Net Pymt. this Estimate 1,355,090.22