Dept. of Trans. PROGRESS Serial No. Contract No. 12-052-11-42 11-2T0924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 83% 11-SD-15-M10.4/R21.2 Federal Project: NONE Progress payment No. 43 Payment period ending: 02-20-12 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA, STE 200 SAN DIEGO CA 92126 Escrow No. 02397 Total Estimate This Estimate 1. Contract Itms Without Mobil. 55,901,968.99 320,600.25 2.a. Extra Work 9,312,678.24 267,566.73 b. Adjustment Comp. 425,055.34 93,299.24 3. Materials on Hand 189,278.27 1,982.19 4. Earned Subject to Retention 65,828,980.84 683,448.41 5. Mobilization 6,008,008.30 0.00 6. Total Work Completed 71,647,710.87 7. Deductions -45,617.13 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 71,791,372.01 681,448.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 681,448.41