Dept. of Trans. PROGRESS Serial No. Contract No. 12-171-13-05 11-2T0994 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 43% 11-SD-15-M16.4/M19.5 Federal Project: NONE Progress payment No. 05 Payment period ending: 06-20-12 DIVERSIFIED LANDSCAPE CO. 33801 WASHINGTON STREET WINCHESTER CA 92596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 459,702.60 151,260.64 2.a. Extra Work 23,158.59 13,362.53 b. Adjustment Comp. 3. Materials on Hand 18,691.20 -4,658.10 4. Earned Subject to Retention 501,552.39 159,965.07 5. Mobilization 173,063.40 36,434.40 6. Total Work Completed 655,924.59 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 674,615.79 196,399.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 196,399.47