Dept. of Trans. PROGRESS Serial No. Contract No. 14-324-11-59 11-2T1784 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 13% 11-SD-5-35.8/38.5 Federal Project: NONE Progress payment No. 01 Payment period ending: 11-20-14 WESTERN RIM CONSTRUCTORS, INC. 912 S ANDREASEN DRIVE, STE 10 ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,099.04 30,099.04 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 30,099.04 30,099.04 5. Mobilization 27,876.34 27,876.34 6. Total Work Completed 57,975.38 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 57,975.38 57,975.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,975.38