Dept. of Trans. PROGRESS Serial No. Contract No. 14-356-09-16 11-2T1784 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 28% 11-SD-5-35.8/38.5 Federal Project: NONE Progress payment No. 02 Payment period ending: 12-20-14 WESTERN RIM CONSTRUCTORS INC 912 S ANDREASEN DRIVE STE 108 ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 86,985.96 56,886.92 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 86,985.96 56,886.92 5. Mobilization 41,814.50 13,938.17 6. Total Work Completed 128,800.46 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 128,800.46 70,825.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,825.09