Dept. of Trans. PROGRESS Serial No. Contract No. 17-170-14-34 11-2T1784 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 11-SD-5-35.8/38.5 NONE Progress payment No. 028 Payment period ending: 06-20-17 WESTERN RIM CONSTRUCTORS INC. 621 S ANDREASEN DR #B ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 496,074.10 2,521.67 2. a. Extra Work 42,538.20 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 538,612.30 2,521.67 5. Mobilization 55,752.67 0.00 6. Total Work Completed 594,364.97 7. Deductions -7,000.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 587,364.97 4,521.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,521.67