Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-029-11-21 11-2T1784 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-5-35.8/38.5 NONE Progress payment No. 034 Payment period ending: 12-29-17 WESTERN RIM CONSTRUCTORS INC. 621 S ANDREASEN DR #B ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 525,460.10 13,134.93 2. a. Extra Work 42,538.20 0.00 b. Adustment Comp. -6,055.41 -6,055.41 3. Materials on Hand 4. Earned Subject to Retention 561,942.89 7,079.52 5. Mobilization 55,752.67 0.00 6. Total Work Completed 617,695.56 7. Deductions -12,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 605,695.56 -2,920.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -2,920.48