Dept. of Trans. SEMI-FINAL Serial No. Contract No. 18-087-15-04 11-2T1784 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-5-35.8/38.5 NONE Progress payment No. 035 Payment period ending: 12-29-17 WESTERN RIM CONSTRUCTORS INC. 621 S ANDREASEN DR #B ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 525,460.10 0.00 2. a. Extra Work 48,676.48 6,138.28 b. Adustment Comp. -6,055.41 0.00 3. Materials on Hand 4. Earned Subject to Retention 568,081.17 6,138.28 5. Mobilization 55,752.67 0.00 6. Total Work Completed 623,833.84 7. Deductions 0.00 12,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 623,833.84 18,138.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,138.28