Dept. of Trans. PROGRESS Serial No. Contract No. 12-236-09-49 11-2T1804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 26% 11-SD-805-9.4/13.8 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-12 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,827,181.42 778,225.60 2.a. Extra Work 6,160.00 6,160.00 b. Adjustment Comp. -2,000.00 -2,000.00 3. Materials on Hand 4. Earned Subject to Retention 1,831,341.42 782,385.60 5. Mobilization 1,068,750.00 356,250.00 6. Total Work Completed 2,900,091.42 7. Deductions -5,293.55 -5,097.85 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,894,797.87 1,133,537.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,133,537.75