Dept. of Trans. PROGRESS Serial No. Contract No. 13-203-15-16 11-2T1814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 80% 11-SD-805-5.5/9.4 Federal Project: NONE Progress payment No. 14 Payment period ending: 07-20-13 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,499,607.80 1,543,852.49 2.a. Extra Work 1,881,375.37 551,877.25 b. Adjustment Comp. 56,432.91 -34,634.09 3. Materials on Hand 0.00 -15,338.20 4. Earned Subject to Retention 16,437,416.08 2,045,757.45 5. Mobilization 2,920,000.00 0.00 6. Total Work Completed 19,357,416.08 7. Deductions -25,602.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,331,814.08 2,040,757.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,040,757.45