Dept. of Trans. PROGRESS Serial No. Contract No. 14-237-10-42 11-2T1824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 44% 11-SD-805-4.7/5.6 Federal Project: NONE Progress payment No. 18 Payment period ending: 08-20-14 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,419,265.99 1,247,857.65 2.a. Extra Work 414,694.03 10,264.52 b. Adjustment Comp. 1,637.86 0.00 3. Materials on Hand 4. Earned Subject to Retention 15,835,597.88 1,258,122.17 5. Mobilization 3,538,512.50 0.00 6. Total Work Completed 19,374,110.38 7. Deductions -11,000.00 -6,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,363,110.38 1,252,122.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,252,122.17