Dept. of Trans. FINAL Serial No. Contract No. 16-025-14-34 11-2T1834 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-805-5.8/13.0 NONE Progress payment No. 020 Payment period ending: 08-04-15 WESTERN RIM CONSTRUCTORS INC. 912 S. ANDREASEN DR STE 108 ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,985,722.28 0.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 4,985,722.28 0.00 5. Mobilization 283,759.64 0.00 6. Total Work Completed 5,269,481.92 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,269,481.92 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00