Dept. of Trans. PROGRESS Serial No. Contract No. 15-323-13-09 11-2T2004 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 88% Location: Federal Project: 11-SD-805-23.7/27.6 CMLN-6211(106) Progress payment No. 039 Payment period ending: 11-20-15 SKANSKA USA CIVIL WEST CALIFORNIA DISTRICT INC 1995 AGUA MANSA ROAD RIVERSIDE CA 92509 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 65,425,755.00 924,485.00 2. a. Extra Work 2,854,689.03 20,194.14 b. Adustment Comp. -18,463.16 35,181.90 3. Materials on Hand 114,034.50 114,034.50 4. Earned Subject to Retention 68,376,015.37 1,093,895.54 5. Mobilization 6. Total Work Completed 68,261,980.87 7. Deductions -96,365.95 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 68,279,649.42 1,088,895.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,088,895.54