Dept. of Trans. PROGRESS Serial No. Contract No. 18-080-15-26 11-2T2174 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 30% Location: Federal Project: 11-SD-5-R37.4/R46.5 CMST-PL62-1(113) ACIM-051(636) Progress payment No. 014 Payment period ending: 03-20-18 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 77,544,260.99 6,853,482.26 2. a. Extra Work 6,503,635.40 2,115,032.00 b. Adustment Comp. -603,996.94 255,200.00 3. Materials on Hand 671,593.34 -1,640,848.02 4. Earned Subject to Retention 84,115,492.79 7,582,866.24 5. Mobilization 16,950,200.65 0.00 6. Total Work Completed 100,394,100.10 7. Deductions -25,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 101,040,693.44 7,577,866.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,577,866.24