Dept. of Trans. PROGRESS Serial No. Contract No. 19-322-13-35 11-2T2174 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 70% Location: Federal Project: 11-SD-5-R37.4/R46.5 CMST-PL62-1(113) ACIM-051(636) Progress payment No. 034 Payment period ending: 11-20-19 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 141,278,173.99 3,004,912.87 2. a. Extra Work 20,357,032.29 864,674.91 b. Adustment Comp. 2,225,932.76 74,000.00 3. Materials on Hand 1,630,606.66 -42,549.00 4. Earned Subject to Retention 165,491,745.70 3,901,038.78 5. Mobilization 17,842,316.47 0.00 6. Total Work Completed 181,703,455.51 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 183,329,062.17 3,901,038.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,901,038.78