Dept. of Trans. PROGRESS Serial No. Contract No. 21-321-19-12 11-2T2174 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 98% Location: Federal Project: 11-SD-5-R37.4/R46.5 CMST-PL62-1(113) ACIM-051(636) Progress payment No. 058 Payment period ending: 11-20-21 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 16470 W BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 189,193,974.74 1,378,100.43 2. a. Extra Work 26,951,825.47 48,779.32 b. Adustment Comp. 8,133,671.33 130,767.46 3. Materials on Hand 1,078,817.56 -71,063.28 4. Earned Subject to Retention 225,358,289.10 1,486,583.93 5. Mobilization 17,842,316.47 0.00 6. Total Work Completed 242,121,788.01 7. Deductions -111,501.40 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 243,089,104.17 1,486,583.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,486,583.93