Dept. of Trans. PROGRESS Serial No. Contract No. 22-021-16-02 11-2T2174 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 97% Location: Federal Project: 11-SD-5-R37.4/R46.5 CMST-PL62-1(113) ACIM-051(636) Progress payment No. 060 Payment period ending: 01-20-22 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 16470 W BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 192,070,326.73 1,140,294.72 2. a. Extra Work 27,587,652.77 351,536.70 b. Adustment Comp. 8,233,525.41 -13,949.01 3. Materials on Hand 942,650.56 -136,167.00 4. Earned Subject to Retention 228,834,155.47 1,341,715.41 5. Mobilization 17,842,316.47 0.00 6. Total Work Completed 245,733,821.38 7. Deductions -121,501.40 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 246,554,970.54 1,331,715.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,331,715.41