Dept. of Trans. PROGRESS Serial No. Contract No. 22-111-17-12 11-2T2174 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 99% Location: Federal Project: 11-SD-5-R37.4/R46.5 CMST-PL62-1(113) ACIM-051(636) Progress payment No. 063 Payment period ending: 04-20-22 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 16470 W BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 197,519,144.95 2,901,554.26 2. a. Extra Work 28,319,818.76 294,690.41 b. Adustment Comp. 8,245,775.33 -44,603.27 3. Materials on Hand 1,132,366.98 150,839.25 4. Earned Subject to Retention 235,217,106.02 3,302,480.65 5. Mobilization 17,842,316.47 0.00 6. Total Work Completed 251,927,055.51 7. Deductions -116,936.40 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 252,942,486.09 3,302,480.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,302,480.65