Dept. of Trans. PROGRESS Serial No. Contract No. 22-203-10-36 11-2T2174 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 100% Location: Federal Project: 11-SD-5-R37.4/R46.5 CMST-PL62-1(113) ACIM-051(636) Progress payment No. 066 Payment period ending: 07-20-22 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 200,928,037.42 250,285.53 2. a. Extra Work 29,445,688.95 94,452.97 b. Adustment Comp. 8,591,644.36 104,259.50 3. Materials on Hand 613,604.87 -24,869.60 4. Earned Subject to Retention 239,578,975.60 424,128.40 5. Mobilization 17,842,316.47 0.00 6. Total Work Completed 256,807,687.20 7. Deductions -126,936.40 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 257,294,355.67 424,128.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 424,128.40