Dept. of Trans. FINAL Serial No. Contract No. 23-145-09-25 11-2T2174 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-5-R37.4/R46.5 CMST-PL62-1(113) ACIM-051(636) Progress payment No. 074 Payment period ending: 12-30-22 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 202,327,003.79 0.00 2. a. Extra Work 31,478,371.44 0.00 b. Adustment Comp. 9,366,997.06 0.00 3. Materials on Hand 4. Earned Subject to Retention 243,172,372.29 0.00 5. Mobilization 17,842,316.47 0.00 6. Total Work Completed 261,014,688.76 7. Deductions -128,436.40 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 260,886,252.36 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00