Dept. of Trans. PROGRESS Serial No. Contract No. 19-358-08-14 11-2T2184 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 25% Location: Federal Project: 11-SD-5-R38.4/R47.3 6211-130 Progress payment No. 013 Payment period ending: 12-20-19 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 16470 W BERNARDO DR SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 47,279,596.04 3,880,091.80 2. a. Extra Work 4,685,092.30 596,891.17 b. Adustment Comp. 4,616.00 4,616.00 3. Materials on Hand 655,624.02 402,093.09 4. Earned Subject to Retention 52,624,928.36 4,883,692.06 5. Mobilization 21,280,000.00 0.00 6. Total Work Completed 73,249,304.34 7. Deductions -3,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 73,901,928.36 4,883,692.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,883,692.06