Dept. of Trans. PROGRESS Serial No. Contract No. 20-056-15-00 11-2T2184 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 28% Location: Federal Project: 11-SD-5-R38.4/R47.3 6211-130 Progress payment No. 015 Payment period ending: 02-20-20 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 16470 W BERNARDO DR SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 55,122,807.76 4,817,069.18 2. a. Extra Work 4,722,712.94 37,620.64 b. Adustment Comp. 8,913.60 4,297.60 3. Materials on Hand 841,411.87 117,698.15 4. Earned Subject to Retention 60,695,846.17 4,976,685.57 5. Mobilization 21,280,000.00 0.00 6. Total Work Completed 81,134,434.30 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 81,965,846.17 4,976,685.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,976,685.57