Dept. of Trans. PROGRESS Serial No. Contract No. 21-051-14-56 11-2T2184 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 51% Location: Federal Project: 11-SD-5-R38.4/R47.3 6211-130 Progress payment No. 027 Payment period ending: 02-20-21 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 16470 W BERNARDO DR SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 106,277,952.49 4,418,540.15 2. a. Extra Work 11,016,346.04 2,086,620.09 b. Adustment Comp. 17,896.00 0.00 3. Materials on Hand 1,244,251.61 78,984.68 4. Earned Subject to Retention 118,556,446.14 6,584,144.92 5. Mobilization 22,400,000.00 0.00 6. Total Work Completed 139,712,194.53 7. Deductions -19,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 140,937,446.14 6,584,144.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,584,144.92