Dept. of Trans. PROGRESS Serial No. Contract No. 21-322-08-42 11-2T2184 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 71% Location: Federal Project: 11-SD-5-R38.4/R47.3 6211-130 Progress payment No. 036 Payment period ending: 11-20-21 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 16470 W BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 155,343,523.16 2,581,540.96 2. a. Extra Work 12,458,556.01 435,292.79 b. Adustment Comp. 82,982.20 -10,000.00 3. Materials on Hand 1,434,015.13 227,156.51 4. Earned Subject to Retention 169,319,076.50 3,233,990.26 5. Mobilization 22,400,000.00 0.00 6. Total Work Completed 190,285,061.37 7. Deductions -19,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 191,700,076.50 3,233,990.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,233,990.26